폐혈회수장치 설치 시공
HRSG Erection
최적의 시스템이 되도록 설치•시공함으로써 고품위 고효율 발전설비가 되도록 최선을 다하고 있으며,
녹색미래에너지 생산이 되기 위한 선도적 노력을 하고 있습니다.
Scope of Work
HRSG Erection Work, Power Block & BOP Piping Work,
Mechanical Erection Work
Capacity
HRSG - 3,800 Ton
HRSG Piping – 16,000 DI
Steel Structure – 1,800 Ton
Power Block Equipment – 3,200 Ton
Power Block Piping – 24,000 DI
BOP Equipment – 1,700 Ton
BOP Piping – 14,000 DI
Duration
Mar 2003 – May 2005
Scope of Work
HRSG Erection Work, Power Block & BOP Piping Work
Capacity
HRSG - 5,580 Ton
HRSG Piping – 32.000 DI
Power Block Equipment – 3,700 Ton
Power Block Piping – 41,000 DI
BOP Equipment – 1,780 Ton
BOP Piping – 1,270 DI
Duration
Sep 2005 – May 2007